Is it a valid compensation event? · Module 1 · Lesson 3 of 4
Test the instruction against the Scope
Why it matters
Of Dana's two May messages, only one cost GBP 18,315
Dana Whitfield is the Project Manager, Raj Patel Merrow Vale's planner. Which message changed the Scope?
- Tue 5 MayShe says the Scope bars Raj's Sunday 17 May pour.
- Mon 11 MayShe limits Mill Lane heavy vehicles at school times.
Source: ECC 11.2(16), 60.1(1).
The rule
Compare the instruction with the Scope as it stood just before it
Three comparisons are common and wrong. Judge each, then open it.
“The Project Manager gives an instruction changing the Scope” (60.1(1))
Compare it with the price?
With the programme?
With what was said at tender?
With the Scope just before?
Source: ECC 11.2(16), 14.1, 60.1(1). ECC Option C 55.2.
The rule
Adding, removing or altering is a change, and repeating the Scope is not
A removed choice counts too. It adds a constraint.
A new requirement or constraint.
Work taken out, or a choice removed.
What the Scope describes or limits.
What the Scope already says.
Source: ECC 11.2(16), 60.1(1).
The rule
Settle the change before arguing about cost
Still valid with no effect. It needs no quotation.
“has no effect upon Defined Cost, Completion or meeting a Key Date” (61.2)
- 1
Does it change the Scope?
If no:Not a 60.1(1) eventIf yes, go on to question 2. - 2
Any effect on cost or time?
If no:Valid, no quotationIf yes, go on to the outcome. - Valid, quotations instructed
Source: ECC 60.1(1), 61.2, 63.1.
See it on the project
Dana's 11 May instruction alters a constraint, so it changes the Scope
Leila, Merrow Vale's commercial manager, puts the instruction beside the Scope just before it.
| The Scope just before | Dana's instruction | |
|---|---|---|
| VehiclesChanged | Deliveries | Vehicles over 7.5 tonnes |
| WhereChanged | The Mill Lane entrance | The whole of Mill Lane |
| MorningChanged | 08:15 to 09:00 | 08:00 to 09:15 |
| AfternoonNew | No limit | 14:45 to 15:45 |
| DaysSame | School days | School days |
Dana notified CE012 that day. The quotation of GBP 18,315 (Defined Cost GBP 16,500 plus the Fee at 11%) was accepted on 3 June.
Source: ECC 11.2(16), 60.1(1), 61.1, 61.2, 63.1.
Try it
Sort six Aldermere cases into compensation event or not
Run the test on each case. The reason shows after each answer.
…
A compensation event
- Dana instructs a flatter embankment slope than the drawings show.
- Dana instructs Merrow Vale to leave out part of the works.
- Dana instructs a new limit on noise from the Mill Lane site.
Not a compensation event
- Dana reminds Merrow Vale of the delivery ban the Scope already sets.
- Dana tells Gareth Lyle, Merrow Vale's site agent, by phone to start work at 07:00.
- Aldermere Water's designer emails Merrow Vale a revised detail.
Source: ECC 13.1, 13.2, 14.2, 14.3, 60.1(1).
Quick check · Try it
Two questions on what you have just covered
Sunday, then cost.
2 questions to answer
Source: ECC 11.2(16), 14.1, 31.3, 60.1(1), 60.1(8), 61.2, 63.1. ECC Option C 55.2.
Recap
Put each instruction beside the Scope just before it, never beside the price
Three habits for Monday. Go deeper has a model notice.
On Monday at work
- Write the Scope clause next to each instruction before anyone discusses cost.
- Mark what the instruction adds, removes or alters.
- Send a 61.3 notification if Dana has not notified the change.
In the Toolkit: NEC4 ECC Notice Letters (zip) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 11.2(16), 60.1(1), 61.1, 61.3.
Go deeper (optional)
Grey areas turn on the Scope, not the price
Three questions practitioners ask.
Dana picked one of two products the Scope allowed. A change?
ECC 11.2(16), 61.2
More of the same work turned up. A change?
ECC 60.1(1), 60.1(12)
Dana omits work to give it to another firm. Can she?
ECC 60.1(1), 63.4
Source: ECC 11.2(16), 60.1(1), 60.1(12), 61.2, 63.4. ECC Option C 54.1.
Go deeper (optional)
Notify it yourself
Letter 02 in the Toolkit. Send it on its own, through the portal (13.7).
To: [Project Manager]
We notify a compensation event under 60.1(1).
Your [date] instruction requires [what it asks for].
Before, [Scope clause] said [what it said].
Reply within one week (61.4).
Source: ECC 13.2, 13.7, 60.1(1), 61.3, 61.4.