Is it a valid compensation event? · Module 1 · Lesson 4 of 4
Drafting that starts the argument
Why it matters
Two of Aldermere's compensation events began with how the Scope was written
Neither came from a change of mind. Both came from loose drafting, and both changed the Prices.
Source: ECC 17.1, 60.1(1), 63.10.
The rule
Performance drafting leaves the method open, prescriptive fixes it
One requirement, written both ways. The risk sits differently each time.
Performance: method open
A flotation check at the highest groundwater level in the Site Information.
Prescriptive: answer fixed
A 600 mm base slab, in Merrow Vale's design statement.
Its writer carries the risk. It failed (Module 4).
Source: ECC 11.2(16), 17.1, 60.1(1).
The rule
Most arguments start with one of six drafting habits
If you write or check Scope, look for these first. Two of them cost Aldermere money.
| What goes wrong | |
|---|---|
| Vague wordsSuch as “as required” or “suitable” | Read two ways |
| Silence on a detailThe inside of the culvert joints | CE011, GBP 26,085 |
| Work to someone's satisfactionThe Project Manager's, with no test | No standard |
| No clear design splitDrawings that do not say who designs what (21.1) | Whose Scope? |
| One rule written twiceDrawing C-210 and specification 5.12 | CE009, GBP 11,100 |
| Paper in the wrong placeTender answers in emails, rules in the Site Information | Not Scope |
Source: ECC 11.2(16), 11.2(18), 17.1, 21.1.
See it on the project
Aldermere Water wrote two requirements as tests that pass or fail
Judge each, then open it. Here the drafting worked.
Key Date 1 asks for the embankment ready for planting. Measurable?
The wet well's flotation check. Measurable?
Source: ECC 11.2(16). Contract Data part one.
Try it
Sort six lines of draft Scope: measurable, or open to argument
Imagine you are checking the Scope before tender. The reason shows after each answer.
…
Measurable
- Reinstate the verge with 100 mm of topsoil and seed it within two weeks.
- Compact the fill in layers no thicker than 150 mm.
Open to argument
- Make good the verge as required.
- Finish the chamber walls to the Project Manager's satisfaction.
- Seal the joints where necessary.
- A tender answer on the fence material, left in an email.
Source: ECC 11.2(16), 17.1.
Quick check · Try it
Two questions on what you have just covered
Clash, then method.
2 questions to answer
Source: ECC 11.2(16), 17.1, 60.1(1).
Recap
Write each requirement once, in one document, as a test someone can pass or fail
Three checks for any Scope you write.
On Monday at work
- Replace vague words and satisfaction clauses with a measurable test.
- State each requirement once, in one listed document (17.1).
- Fold every tender answer into a listed document before the Contract Date (11.2(16)).
In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 11.2(16), 17.1, 21.1.
Go deeper (optional)
Three drafting traps practitioners ask about
Opinion is split on the first. Take advice before you rely on it.
The work is subject to Dana's satisfaction. Can she ask for more?
A tender answer never reached a listed document. Does it bind?
Dana told us how to meet a performance we missed. Change or not?
Source: ECC 10.1, 10.2, 11.2(16), 63.1.
Go deeper (optional)
Courts read the Scope as written, so a buried requirement still binds
Three cases, the amendments and what changed from NEC3.
What did MT Højgaard (2017) decide?
What does Wales and West (2014) show?
Is Atkins (2013) about more of the same work?
Which amendments narrow 60.1(1)?
What changed from NEC3?
Source: MT Højgaard v E.ON (2017). Wales and West v PPS (2014). Atkins v Secretary of State for Transport (2013). ECC 13.2, 14.2, 60.1(1).