Is it a valid compensation event? · Module 1 · Lesson 2 of 4
What the Scope is and who changes it
Why it matters
On 5 January 2026 Leila, Merrow Vale's commercial manager, reads what binds it
Merrow Vale's GBP 8,400,000 price relied on all four. Only some are Scope.
Source: ECC 11.2(16), 14.3.
The rule
Scope describes the works or limits how
Nothing else is Scope, however much the price relied on it.
It “specifies and describes the works” (11.2(16)), or sets a constraint on the work.
Not Scope: Site Information, Activity Schedule, programme, tender emails.
Source: ECC 11.2(16), 11.2(18), 14.1. ECC Option C 55.2. Contract Data parts one and two.
The rule
Four things make a change count, then two follow
Dana is the Project Manager. All four must hold.
- Dana instructs14.2, 14.3
- In a lasting form13.1
- Through the portal13.2
- It changes the Scope60.1(1)
A duty (27.3).
With it (61.1).
No eight-week bar (61.3).
Source: ECC 13.1, 13.2, 14.2, 14.3, 27.3, 60.1(1), 61.1, 61.3.
See it on the project
Dana or her named delegate can change the Scope, so can anyone else at Aldermere?
Decide each, then open it.
“may give an instruction to the Contractor which changes the Scope” (14.3)
Tom Barrow, the Supervisor?
Aldermere Water, the Client, by letter?
The Client's designer, by email?
A decision at an early warning meeting?
Source: ECC 14.2, 14.3, 15.4.
Try it
Sort seven Aldermere papers into Scope and not Scope
Ask where each paper sits. The reason shows after each answer.
…
Scope
- The specification, listed in Contract Data part one.
- Merrow Vale's tender design statement, listed in part two.
- Dana's instruction of 11 May 2026 on heavy vehicles.
Not Scope
- An emailed answer to a tender query that no listed document holds.
- The three borehole logs in the Site Information.
- The Activity Schedule, with Merrow Vale's lump sums.
- The Accepted Programme, as Dana last accepted it.
Source: ECC 11.2(16), 11.2(18), 14.1, 20.1. ECC Option C 55.2.
Quick check · Try it
Two questions on what you have just covered
Scope, then the portal.
2 questions to answer
Source: ECC 11.2(16), 13.2, 14.1.
Recap
Check where a paper sits and who sent it before acting on it
Three habits that keep the Scope file right.
On Monday at work
- List the documents the Contract Data names as Scope (11.2(16)).
- Add each instruction to it on the day it arrives.
- Act only on Dana's instructions through the portal, or a named delegate's (14.3).
In the Toolkit: NEC4 Compensation Event Register (ECC and ECS) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 11.2(16), 13.2, 14.2, 14.3.
Go deeper (optional)
Key Dates and delegation each have their own rule
Two points that catch people out.
Dana moves a Key Date. Is that a 60.1(1) event?
ECC 14.3, 60.1(4)
What must a delegation notice say?
ECC 14.2
Source: ECC 13.2, 14.2, 15.4, 60.1(1), 60.1(4).