NEC4 Payment and Defined Cost Masterclass · Lesson 2 of 3
From cost to cash
Why it matters
Merrow Vale has paid GBP 1,905,000, and the 1 June payment is GBP 646,020
Merrow Vale is the Contractor, Aldermere Water the Client and Dana Whitfield the Project Manager. How do the figures join?
Source: ECC 51.1. ECC Option C 11.2(31).
The rule
Defined Cost is the listed cost, less Disallowed Cost
One box each.
Listed in the Schedule of Cost Components.
Listed, but a ground such as missing records removes it.
Not listed. The Fee covers it.
“the cost of the components in the Schedule of Cost Components less Disallowed Cost” (11.2(24))
Source: ECC 52.1. ECC Option C 11.2(24), 11.2(26).
The rule
Under Option C, payment starts from forecast Defined Cost
Five steps, in this order.
- Defined CostPaid, plus the Project Manager's forecast.C 11.2(31)
- Plus the FeeAt the fee percentage.Clause 11.2(10)
- Less retention3% over GBP 400,000.Clause X16.1
- Amount dueThe running total.Clause 50.3
- PaymentThe change since last time.Clause 51.1
Source: ECC 11.2(10), 50.3, 51.1, X16.1. ECC Option C 11.2(31).
See it on the project
On 1 June 2026 the cost builds up, then the earlier amount due comes off
Watch the total climb, then fall back to the payment.
The 1 June 2026 assessment, GBP
“the total Defined Cost which the Project Manager forecasts will have been paid” (11.2(31))
Source: ECC 11.2(10), 50.3, 51.1, 51.2, X16.1. ECC Option C 11.2(31).
See it on the project
The target stays beside the payment path until the share is worked out
Work out the share before you look.
Target and Price for Work Done to Date, GBP
At the end Merrow Vale beats the target by GBP 272,000. What is its share?
Is the GBP 136,000 paid through the monthly payments?
Source: ECC Option C 54.1, 54.3, 54.4. Aldermere Contract Data.
Try it
Sort the costs Dana checks on 8 July 2026 for the four weeks to 29 June
Does a component cover it? Then, does a ground take it out? Each answer names the ground.
…
Defined Cost
- Northway's hire of the 30 tonne excavator working on Site
- Recasting a culvert base slab before Completion
Disallowed Cost
- A spare excavator kept three weeks after Dana asked for it to go
- Kestrel hours for the week of 15 June, with no timesheets
- A steel surcharge the fencing supplier's contract does not require
Not Defined Cost
- Rent for the Kelworth office
- GBP 1,900 that an early payment discount took off concrete invoices
Source: ECC 52.1. ECC Option C 11.2(24), 11.2(26).
Quick check · Try it
Two questions on what you have just covered
Work each one out before you pick. The figures are on the money map.
2 questions to answer
Source: ECC 11.2(10), 50.1, 50.2, X16.1. ECC Option C 11.2(31).
Recap
Follow every payment from Defined Cost to cash
Four checks for any certificate. Next: who does what, and when.
On Monday at work
- Start from Defined Cost paid, then add the forecast.
- Add the Fee before you take off retention.
- Pay the change in the amount due, not the total.
- Keep the target out of the payment.
In the Toolkit: NEC4 Application for Payment (ECC and ECS, Options A to F) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 11.2(10), 50.3, 51.1, X16.1. ECC Option C 11.2(31), 54.1.
Go deeper (optional)
Three edges of the money map
Three common questions. The first is a what-if.
Sent Friday 26 June, received Monday 29 June. Paid when?
ECC Option C 11.2(31), 52.2
Whose forecast sets the payment?
ECC Option C 11.2(31), 20.4
Does payment stop at the target?
ECC Option C 54.1
Source: ECC 52.2. ECC Option C 11.2(31), 20.4, 54.1.