NEC4 Payment and Defined Cost Masterclass · Module 1 · Lesson 3 of 4

What counts as Defined Cost

6 screensAbout 6 minutes

Why it matters

Leila's ledger holds nine costs, so which of them reach Dana's certificate?

Leila Moss is Merrow Vale's commercial manager and Dana Whitfield the Project Manager.

GBP 1,905,000of paid by 1 June 2026
11%the , added on top
Paying a cost does not make it Defined Cost.

Source: ECC 52.1. ECC Option C 11.2(24).

The rule

Test each cost: component, price, ground

In this order.

Listed in the , spent to .

  1. Component?listed11.2(24)
  2. Price?Contract Data rate, or competitively tendered or market price52.1
  3. Ground?Disallowed Cost11.2(26)

takes out cost a ground names. Discounts, rebates and recoverable tax come off (52.1).

Source: ECC 52.1. ECC Option C 11.2(24), 11.2(26). Schedule of Cost Components.

The rule

The Fee covers profit and every cost that is not Defined Cost

The is Defined Cost times the fee percentage. Merrow Vale, the Contractor, built its 11% like this.

“not included in the Defined Cost are treated as included in the Fee” (52.1)

What Merrow Vale's 11% fee percentage covers, percent of Defined Cost

Head office
4.5%
People based off Site
1.5%
Insurance premiums
1.0%
Other costs the Schedule leaves out
1.0%
Profit
3.0%
0%1%2%3%4%5%

Source: ECC 11.2(10), 52.1. Aldermere Contract Data.

See it on the project

Two salaries in the ledger turn on where each person normally works

Decide each one as Dana would, then check.

Gareth Lyle, the site agent, works from the site offices. How much of his salary counts?

All of it. The site offices are in the , his normal place of working (component 1).

Leila Moss is based at Kelworth and on Site two days a week. How much of hers counts?

40%, for her two days a week on Site. Her Kelworth days sit in , as the Contract Data lists nobody (52.1).

Source: ECC 52.1. Schedule of Cost Components, component 1. Aldermere cost file.

Try it

Sort seven more lines from Merrow Vale's ledger

Use the three questions. Each answer tells you why.

Line 1 of 7

…

Source: ECC 52.1. ECC Option C 11.2(26). Schedule of Cost Components, items 11 and 14.

Recap

Ask which component before you ask which ground

Next, why Option C is not cost-plus.

On Monday at work

  • Check each ledger line against a component before it goes in the application.
  • Take rebates, discounts and recoverable tax off Defined Cost.
  • Keep timesheets for every agency hour you apply for.

In the Toolkit: NEC4 Application for Payment (ECC and ECS, Options A to F) (Excel) Members

Next lesson: Why Option C is not cost-plus

Your place is kept in this browser. Create a free account to keep it on every device.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: ECC 52.1. ECC Option C 11.2(24), 11.2(26).

Go deeper (optional)

Disallowed Cost is a closed list

Four points for later.

Why is office rent not Disallowed Cost?

No component covers it, so it was never Defined Cost. Disallowed Cost is a closed list of grounds that strips out cost a component would otherwise admit. Calling a Fee item Disallowed Cost muddles the two.

Clause 52.1. Option C 11.2(26)

What does Disallowed Cost cost under E?

Side case: on a job with an 8% fee, GBP 20,000 of hire as Disallowed Cost costs the Contractor GBP 21,600, the cost plus its Fee. No share softens it.

Option E 11.2(26). Clause 11.2(10)

How does Option F differ?

Defined Cost is what is due to , plus prices for the Contractor's own work. Paying a Subcontractor for the Contractor's management is Disallowed Cost.

Option F 11.2(25), 11.2(27)

Did NEC3 work the same way?

NEC3 had separate fee percentages for subcontracted and direct work. NEC4 has one, so NEC3 build-ups mislead.

Clause 11.2(10)

Source: ECC 11.2(10), 52.1. ECC Option C 11.2(26). ECC Option E 11.2(26). ECC Option F 11.2(25), 11.2(27).