NEC4 Payment and Defined Cost Masterclass · Module 1 · Lesson 4 of 4
Why Option C is not cost-plus
Why it matters
Why does Merrow Vale's GBP 136,000 share wait for the end of the job?
The target decides the final bill.
Source: ECC Option C 54.1, 54.2. Aldermere Contract Data.
The rule
At the end the saving or overrun is split through the share ranges
Merrow Vale's share in each share range.
“The difference is divided into increments falling within each of the share ranges” (54.1)
of the saving
of each pound saved or overspent
of the overrun
Source: ECC Option C 54.1 to 54.4. Aldermere Contract Data.
The rule
A late notice keeps the cost paid but freezes the target
Events caused by the Project Manager or the Supervisor sit outside the bar.
“within eight weeks of becoming aware that the event has happened” (61.3)
In time
The Completion Date, a Key Date and the Prices can move.
Late
None can move, but the cost is paid.
Source: ECC 61.3. ECC Option C 11.2(31), 54.1.
See it on the project
Without the CE007 notice, Merrow Vale would have lost GBP 68,600
One notice on 6 March 2026 protected GBP 40,600 of share and GBP 28,000 of delay damages.
Aldermere's final assessment, with and without the CE007 notice, GBP
Without CE007 the target is GBP 81,200 lower and Completion is eight days late.
Source: ECC 61.3, X7.1. ECC Option C 54.1, 54.2. Aldermere Contract Data.
See it on the project
Notify each event separately (13.7), inside eight weeks
Change the date. The eight weeks run from awareness.
To: Dana Whitfield, Project Manager
From: [your name], Merrow Vale
Date: 6 March 2026
Event: physical conditions (60.1(12)).
Found 3 March 2026: old foundations in the Station Road culvert trench.
In the Toolkit: Letter 02
- Last day to notifyeight weeks after Merrow Vale became aware
Source: ECC 13.7, 60.1(12), 61.3.
Quick check · The target
Two questions on what you have just covered
Two situations.
2 questions to answer
Source: ECC Option C 11.2(31), 54.3, 54.4. ECC 61.3.
Recap
Protect the target as hard as you protect the payment
That completes the lessons. Next, the module check.
On Monday at work
- Notify every compensation event inside eight weeks, paid or not.
- Track the Price for Work Done to Date against the target every month.
- Check for a Z clause that caps payment at the target.
In the Toolkit: NEC4 ECC Notice Letters (zip) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 61.3. ECC Option C 54.1.
Go deeper (optional)
Payment runs on above the target unless a Z clause stops it
Two points for later. Skip them if you are short of time.
Is interim payment capped at the target?
Option C 54.1, 54.3
Can a Client change that?
Option Z
Source: ECC Option C 54.1, 54.3. Option Z. Doosan Enpure v Interserve (2019).
Go deeper (optional)
Payment rules sit in five places
A map for later modules.
What do the core clauses hold?
What does the main Option add?
Options C to F. Share: C and D
Where do secondary Options fit?
Schedule of Options
What does the Contract Data set?
Contract Data
What does the Scope add?
Scope
Source: ECC 50 to 53. ECC Options C to F 20.4, 50.9, 52.4. ECC Option C 54.1 to 54.4. Schedule of Options. Contract Data.