NEC4 Payment and Defined Cost Masterclass · Module 1 · Lesson 2 of 4
Six ways to value work
Why it matters
Why did CE007's GBP 81,200 never reach the 1 June payment?
Six main Options, two ways to pay.
Source: ECC Option C 11.2(31), 11.2(32). Aldermere Contract Data.
The rule
Options A and B pay for work done
The Contractor carries the cost risk.
Option A: activity schedule
Lump sums on the Activity Schedule. Only completed ones are paid.
Option B: bill of quantities
Bill of Quantities rates for completed quantities, plus completed parts of lump sums.
Source: ECC Option A 11.2(23), 11.2(29), 11.2(32). ECC Option B 11.2(30), 11.2(33).
The rule
Options C to F pay Defined Cost forecast to be paid, plus the Fee
The forecast runs to the next assessment date. Cost paid after it waits for a later certificate.
“the total Defined Cost which the Project Manager forecasts will have been paid” (11.2(31))
| The Prices | Share at the end | |
|---|---|---|
| Option CAldermere | Activity lump sums: the target | Yes |
| Option D | A bill, remeasured: the target | Yes |
| Option E | A forecast only | None |
| Option F | A forecast only | None |
Who carries a cost overrun, percent
Shares follow the Contract Data, 50% in Aldermere's main range. Under B, quantity risk stays with the Client.
Source: ECC Options C to F 11.2(31). ECC Options C, D and E 11.2(24). ECC Option F 11.2(25). ECC Option D 11.2(35). ECC Options E and F 11.2(34).
See it on the project
Dana must decide where CE007's GBP 81,200 goes at 1 June 2026
Decide as Dana Whitfield, the Project Manager, would, then check.
Aldermere at 1 June 2026, GBP
Should the 1 June payment include CE007's GBP 81,200?
Suppose a 20.4 forecast passes the target. Should Dana cut the payment?
Source: ECC Option C 11.2(31), 11.2(32), 20.4. Aldermere Contract Data.
Quick check · Six ways to value work
Two questions on what you have just covered
Two side cases.
2 questions to answer
Source: ECC Option B 11.2(30), 60.4. ECC Option A 11.2(29).
Recap
Name the main Option before you check a single figure
Next, what counts as Defined Cost.
On Monday at work
- Read the main Option in the Contract Data and set it on the Setup tab.
- Options A and B: check what is complete. C to F: check the forecast.
- Keep Merrow Vale's 20.4 forecast apart from Dana's payment forecast.
In the Toolkit: NEC4 Application for Payment (ECC and ECS, Options A to F) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC Options A to F 11.2(29) to 11.2(31). ECC Option C 20.4.
Go deeper (optional)
Under Option A, the size and spread of activities matter
Three practice points for Option A.
What do too few activities do?
Option A 11.2(29), 55.4
Can a cash-flow revision be refused?
Option A 55.3, 55.4. Clause 60.1(9)
When is a defective activity complete?
Option A 11.2(29). Clauses 43.2, 50.1
Source: ECC 43.2, 50.1, 60.1(9). ECC Option A 11.2(29), 55.3, 55.4.
Go deeper (optional)
A new bill rate needs three tests
A new rate can be lower too.
- Not caused by a Scope change.
- Defined Cost per unit changes.
- Rate × final quantity tops 0.5% of the Prices at the Contract Date.
Source: ECC 60.1(1). ECC Options B and D 60.4.