NEC4 Payment and Defined Cost Masterclass · Module 1 · Lesson 1 of 4
The money map
Why it matters
Dana certifies GBP 646,020 on 1 June 2026, so where does that figure come from?
Dana Whitfield is the Project Manager. Every ECC payment comes from one short chain of figures. Follow it once.
How the amount due climbed, GBP
Source: ECC 50.3, 51.1. Aldermere Contract Data.
The rule
Three figures build every payment
Prices are not payments.
- PricesA lump sum per activity. Their total is the target.Option C 11.2(32)
- Price for Work Done to DateWhat the Contractor has earned so far.Option C 11.2(31)
- Amount dueThe Price for Work Done to Date, plus and minus other sums.Clause 50.3
Source: ECC 50.3. ECC Option C 11.2(31), 11.2(32).
The rule
Each payment is the change in a running total
A negative step is paid back.
“Other payments are the change in the amount due since the previous assessment” (51.1)
The first certificate pays the whole amount due.
Source: ECC 51.1.
See it on the project
Dana counts cost paid by 1 June, plus what she forecasts before 29 June
Watch it build: Defined Cost, the Fee, then retention and last month's amount due come off.
Dana's assessment at 1 June 2026, GBP
The forecast covers the June payroll, Tarnbeck Piling's GBP 112,000 due on 22 June and other invoices.
Source: ECC 11.2(10), 50.3, 51.1, X16.1. ECC Option C 11.2(31). Aldermere Contract Data.
See it on the project
Dana's forecast to 29 June moves the payment by more than itself
Move her forecast and watch the Fee and retention follow it.
Her real forecast was GBP 595,000. Try the two ends.
Source: ECC 11.2(10), 51.1, X16.1. ECC Option C 11.2(31). Aldermere Contract Data.
Try it
Sort each change: does it move the 1 June payment, or only the target?
Have a go before you look back. Each answer says why.
…
Moves the payment
- Dana forecasts GBP 100,000 less to be paid before 29 June.
- Merrow Vale, the Contractor, pays Tarnbeck Piling GBP 112,000 on 22 June.
- Retention grows as the Price for Work Done to Date grows.
Moves only the target
- Compensation event CE007 adds GBP 81,200 to the Prices on 5 May.
- Two smaller compensation events, CE009 and CE011, are implemented by 1 June.
Source: ECC 50.3, X16.1. ECC Option C 11.2(31), 11.2(32).
Quick check · The money map
Two questions on what you have just covered
Two Aldermere cases.
2 questions to answer
Source: ECC 11.2(10), 51.1, X16.1. ECC Option C 11.2(31).
Recap
Read every certificate as a chain from cost to the payment
Next, how each main Option measures the work.
On Monday at work
- Start from the last certificate's amount due, not the application.
- Check each payment is the step since the last amount due.
- Under Option C, keep the target out of the monthly figures.
In the Toolkit: NEC4 Application for Payment (ECC and ECS, Options A to F) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 50.3, 51.1. ECC Option C 11.2(31).
Go deeper (optional)
Part of every Option C payment pays for cost not yet paid
Two harder points for later. Skip them if you are short of time.
Is the forecast in an Option C payment an advance?
Option C 11.2(31). Clause 51.1
Does an over-forecast carry interest?
Clauses 51.1, 51.3
Source: ECC 51.1, 51.3. ECC Option C 11.2(31).