NEC4 Contract Preparation · Module 1 · Lesson 3 of 4

Services, supply and other forms

7 screensAbout 5 minutes

Why it matters

Beyond the works Aldermere Water buys design, upkeep and small jobs, so which forms fit?

Each purchase beyond the works has its own NEC4 form.

GBP 620,000of design, let first
GBP 1,450,000of upkeep in five years by Selbrook, a maintenance firm
3 supplierson a framework for small jobs

Source: Aldermere Water budget, 15 January 2024. Aldermere contract map, 29 January 2024. Aldermere Water, June and October 2025.

The rule

Services have main and short forms

Advice or upkeep? Then how big?

PSCAny consultant

Options A, C or E.

PSSCSmall brief

Time charge or price list.

TSCTerm upkeep

Options A, C or E.

TSSCSimple upkeep

Priced items, rates.

Goods follow suit: the for high value items, the for simple ones.

Source: NEC4 service and supply product pages.

The rule

A framework sets up suppliers, and each job needs an order

A framework is not an order.

FC

Each supplier waits “until it has received a Work Order or Time Charge Order” (FC 20.3).

  1. Frameworka set term
  2. Selectionthe Client picks oneFC 21.1
  3. OrderWork or Time ChargeFC 20.3
  4. The jobECC, ECSC or PSSC

Source: FC 11.2(4), 11.2(5), 20.3, 21.1. NEC4 FC product page.

The rule

One contract, or shared targets over many

Three ways to join firms beyond a chain. Tap each one.

  1. Who signsThe Client and one contractor.
  2. What it doesOne firm designs, builds and then runs the asset, so it answers for how the asset performs.
  1. Who signsThe Client and several partners, all in one contract.
  2. What it doesCost is reimbursed, with a performance regime on top. An takes the decisions.

“An Own Contract is a contract between two Partners” (X12.1(3))

  1. What it doesShared targets over each ’s own contract. Not with .
    Clause X12.4(1)

Source: ECC X12.1(3), X12.4(1), Schedule of Options. NEC news, April 2017 and June 2018.

See it on the project

Designer in 2024, services in 2025

Decide the last one, then tap.

  1. 2 April 2024 Option A, Harrowgill's design, GBP 620,000.
  2. 2 June 2025 Option A, Selbrook, GBP 1,450,000 over five years.
  3. 1 December 2025, Tom Barrow, the .

Surveys and planting keep coming up. One framework, or a contract each time?

A framework. Aldermere Water’s starts on 1 October 2025. Each job still needs its own order, such as the GBP 9,800 survey by Pennyfold, a framework supplier (FC 20.3).

Source: Aldermere Water, April 2024 to December 2025.

Try it

Sort each service into its NEC4 contract

Ask two things of each job: advice or upkeep, and how big and risky.

Service 1 of 5

…

Source: NEC4 PSC, PSSC, TSC and TSSC product pages.

Recap

Match each service to its family, then its size

Habits for the other lines.

On Monday at work

  • List the needs besides the works: design, upkeep, goods, small orders.
  • Use the for a staged design brief. With no consultant, the names what the Contractor designs (21.1).
  • Plan upkeep early: manuals, training and spares in the works Scope.

In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members

Next lesson: Drawing the contract map

Your place is kept in this browser. Create a free account to keep it on every device.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023, unless another NEC4 contract is named. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: ECC 11.2(2), 21.1. FC 20.3. NEC4 product pages.

Go deeper (optional)

Term work needs a term form

Harder points for later. Skip them if short of time.

Can term maintenance go on a lump sum?

Risky. In Atkins v Secretary of State for Transport (2013) highway upkeep was a lump sum. Each pothole was tested alone, so far more potholes were no .

Atkins (2013)

A , or an and then a TSC?

A DBOC keeps one firm answerable for years of running. Two contracts leave the handover, with its manuals, training and spares, to the Client. The DBOC’s main Options are A, C and E. The has none, and reimburses cost with a performance regime on top.

NEC4 DBOC and ALC product pages

When does the FMC suit better than the TSC?

For buildings. NEC added a facilities management suite in 2021, such as the , as an alternative to the TSC.

NEC4 FMC product page

Source: NEC4 FMC product page. Atkins Ltd v Secretary of State for Transport (2013).