NEC4 Contract Preparation · Module 1 · Lesson 4 of 4

Drawing the contract map

8 screensAbout 7 minutes

Why it matters

Six purchases, GBP 11,200,000: which form fits each?

Dana Whitfield, the Project Manager, drew it on 29 January 2024.

ClientAldermere Water
The works or Subcontracts
Design
Boreholes
Surveys, planting
Maintenance
The Adjudicator
Ruled outOwn networkOne contractor is enough

Source: Aldermere contract map, 29 January 2024.

The rule

Ask four questions of every line

Three pick the family. The fourth picks the size.

  1. Who contracts with whom?Main contract or subcontract.
  2. What is bought?Works, services, goods or an asset.
  3. One job or a term?A term means a term service.
  4. How risky and complex is it?Simple, low risk work takes the short form.

Source: NEC4 contract title pages and product pages.

The rule

The Adjudicator has a contract, and both Parties sign it

W2 matches, and under W3 both Parties appoint the Dispute Avoidance Board.

“The Parties appoint the Adjudicator under the NEC Dispute Resolution Service Contract” (W1.2(1))

Clienta Party

Signs the DRSC.

Contractora Party

Signs it too.

Adjudicator

Under the edition current at the .

Source: ECC W1.2(1), W2.2(3), W3.1(2).

See it on the project

By January 2026 each line is a signed contract

Each line now names a firm.

ClientAldermere Water
PSCApril 2024
Harrowgill
ECSCJune 2024
Quarrymoor
TSCJune 2025
Selbrook
FCOctober 2025
Framework suppliers
December 2025
Tom Barrow
ECCJanuary 2026
Winning tendererECS or ECSSSubcontractors
DRSCBoth Parties
The

Source: Aldermere Water, April 2024 to January 2026.

See it on the project

Answer three questions for your project

Answers save in this browser for Module 11. Then see Aldermere’s choice.

0 of 3 decided

Which NEC4 contract will you use for the main works?

How will you buy design or other professional services?

Who will look after the asset once it is in use?

Source: Strategy builder, stage s1. ECC title page, Schedule of Options.

Try it

Suppose a water company repairs a reservoir: place each line

A new scheme to map. Ask the four questions of each line.

Line 1 of 5

…

Source: NEC4 product pages. NEC comparison note, June 2023.

Quick check · Try it

Two questions on what you have just covered

Each answer tells you why.

Quick checkPick an answer to see if you are right and why
1The Client buys the pumps itself. Which contract fits?
The : high value goods
The ECS: the pumps join the works
The PSC: the maker designs them
2 5 January, starting date 12 January 2026. Which fixes the DRSC edition?
5 January 2026, the Contract Date
12 January 2026, the starting date
The day the first dispute is notified

2 questions to answer

Source: NEC4 SC product page. ECC W1.2(1), W2.2(3).

Recap

Draw the map before you choose any Options

Three habits that start every contract strategy.

On Monday at work

  • Draw one box for each organisation and one line for each contract.
  • Ask the four questions of each line, then write its form on it.
  • Add the Adjudicator as its own line, signed by both Parties (W1.2(1)).

In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members

Next: the module check

Your place is kept in this browser. Create a free account to keep it on every device.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023, unless another NEC4 contract is named. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: ECC W1.2(1). NEC4 product pages.

Go deeper (optional)

Three questions practitioners ask when they draw the map

Harder points for later. Skip them if you are short of time.

Should the be appointed under a PSC or a PSSC?

The ECC does not say. One inspector paid for time suits the PSSC, as for Tom Barrow on 1 December 2025. A team with its own procedures suits the PSC.

Clause 11.2(13)

X12 or the ALC?

X12 lays shared targets over separate two-party contracts. The ALC puts every partner in one contract with an .

Clause X12.1

What changed from NEC3?

The Employer became the Client and Works Information became . NEC4 added the DBOC and the ALC, and filled to .

NEC3 and NEC4 Schedules of Options

Source: ECC 11.2(12), 11.2(13), X12.1, Schedule of Options. NEC3 ECC Schedule of Options.