NEC4 Contract Preparation · Module 1 · Lesson 2 of 4
Subcontractor or supplier
Why it matters
The Contractor will hire a GBP 1,240,000 pump firm, so must Dana accept it first?
Dana, the Project Manager, must know which firms reach her desk.
Source: ECC 11.2(19), 26.2.
The rule
One yes makes a Subcontractor
Stop at the first yes.
- 1
Builds or installs any works?
If yes:SubcontractorIf no, go on to question 2. - 2
Designs any of the works? Not a supplier designing its own goods.
If yes:SubcontractorIf no, go on to question 3. - 3
A needed service in the Working Areas? Not Equipment hire or time-paid people.
If yes:SubcontractorIf no, go on to the outcome. - Not a Subcontractor
Source: ECC 11.2(9), 11.2(14), 11.2(19), 11.2(20).
The rule
The Contractor stays responsible
The Contractor still answers to Dana for all the work.
“responsible for Providing the Works as if it had not subcontracted” (26.1)
- The firmAccepted before appointment. Refused if it stops the Contractor Providing the Works.Clause 26.2
- The documentsSent too, minus pricing information, unless NEC changed only by Z clauses.Clause 26.3
Source: ECC 26.1, 26.2, 26.3.
The rule
Submit each firm by name
Name the firm, the work and the form. Prices only under Options C to F (26.4).
To: [name], Project Manager
Date: [date]
We submit [firm] as a proposed Subcontractor for [the work] (26.2).
It will sign the NEC4 ECS, Option [letter], with only the Z clause changes (26.3).
Source: ECC 26.2, 26.3. ECC Options C to F, 26.4.
See it on the project
Four firms on Aldermere, and one is a Subcontractor
Decide each, then tap to check.
“a person or organisation who has a contract with the Contractor” (11.2(19))
Harrowgill, the designer, under a PSC
Quarrymoor, the borehole driller, under an ECSC
The FC planting firm, working on Site
Cobalt Pumps, installing pumps under an ECS
Source: ECC 11.2(12), 11.2(19), 26.2.
Try it
Sort each firm the Contractor hires: Subcontractor or not
Ask the three questions of each firm. One yes is enough.
…
Subcontractor
- A firm that installs pumps the Contractor bought from a maker.
- An architect who designs the pumping station’s control kiosk.
- A security firm that guards the Working Areas at night.
Not a Subcontractor
- A plant hire firm that hires the Contractor an excavator.
- An agency that supplies labourers paid for the hours they work.
Source: ECC 11.2(9), 11.2(19).
Recap
Test each firm, then submit it before the appointment
Habits for both sides: the Contractor submits and the Project Manager checks.
On Monday at work
- Ask the three questions of every firm the Contractor brings in.
- Submit each Subcontractor by name before it is appointed (26.2).
- Send its subcontract documents too if they go beyond the Z clauses.
In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023, unless another NEC4 contract is named. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 11.2(19), 26.1, 26.2, 26.3.
Go deeper (optional)
Borderline firms and the documents
Harder cases for later. Skip them if short of time.
The pump maker commissions its pumps on Site. Now a Subcontractor?
Clauses 11.2(19), 26.2
The Contractor hires a temporary works designer. Is it a Subcontractor?
Clauses 11.2(9), 23.1
When can Dana refuse the subcontract documents?
Clause 26.3
Source: ECC 11.2(9), 11.2(19), 23.1, 26.2, 26.3.