NEC4 · ECC 11.2(18)
Site Information
What the documents the Contract Data names say about the Site and the land around it. It is treated as known to the Contractor when physical conditions are judged.
“describes the Site and its surroundings” (11.2(18))
On the Aldermere project
Three borehole logs on the culvert line form part of Aldermere's Site Information.
Where you meet it
- Module 8: Compensation events: what they are and how to notify themPractitioner Course
- Module 4: The documents, the Scope and ambiguitiesCase Law
- Module 8: Compensation events: what counts, notices and time barsCase Law
- Module 2: Procurement strategy: the questions to answer firstContract Preparation
- Module 7: Scope and Site Information: drafting that avoids argumentContract Preparation
- Module 8: The tender packageContract Preparation
- Module 3: Ambiguities and inconsistenciesValid compensation events
- Module 5: The other events people argue aboutValid compensation events