NEC4 · ECC 11.2(17)
Site
The area inside the boundaries of the site given in the Contract Data, plus the ground below and the air above that the work affects.
“the area within the boundaries of the site” (11.2(17))
On the Aldermere project
The access date for the whole Site is 12 January 2026.
Also written as
- the Site
Where you meet it
- Module 5: PeoplePayment and Defined Cost
- Module 0: Reading an NEC4 contractContract Preparation · Free
- Module 5: The other events people argue aboutValid compensation events