NEC4 · ECC 11.2(14)
Plant and Materials
Items meant to become part of the works, such as pumps or concrete. Kit that is used but not left in the works is Equipment.
“items intended to be included in the works” (11.2(14))
On the Aldermere project
The pumps and controls Cobalt Pumps Ltd installs at Mill Lane are Plant and Materials.
Where you meet it
- Module 11: Defined Cost, the Schedule of Cost Components and Disallowed CostPractitioner Course
- Module 6: Equipment, Plant and Materials, and ChargesPayment and Defined Cost