planned Completion

The date the Contractor's programme shows for Completion. It may be earlier than the Completion Date, a gap often called terminal float. Delay is measured against it.

On the Aldermere project

Merrow Vale's first CE007 quotation delayed planned Completion by 9 days.

Also written as

  • terminal float

Where you meet it