NEC4 · ECC 31.2
planned Completion
The date the Contractor's programme shows for Completion. It may be earlier than the Completion Date, a gap often called terminal float. Delay is measured against it.
On the Aldermere project
Merrow Vale's first CE007 quotation delayed planned Completion by 9 days.