FIDIC 2017 · FIDIC 3.7.1
Notice of the Parties' agreement
The Engineer's Notice recording an agreement both Parties sign on a matter or Claim. The agreement then binds them like a determination.
“the Engineer shall give a Notice to both Parties of the agreement” (FIDIC 3.7.1)
On the Aldermere project
On 3 June 2026 Dana gave a Notice of the Parties' agreement on Claim 1: EOT 7 days and GBP 76,500.
Where you meet it
- Module 5: Compensation events and ClaimsNEC4 vs FIDIC 2017