NEC4 · ECC X7.1

delay damages

Under Option X7, a fixed daily sum the Contractor pays for each day Completion, or earlier take over, falls after the Completion Date.

On the Aldermere project

Completion came one day late on 26 May 2027, so GBP 4,000 of delay damages was deducted.