FIDIC 2017 · FIDIC 1.1.28
Delay Damages
The Contract Data's daily sum the Contractor owes for late completion, up to a stated maximum. The Employer must claim them under Sub-Clause 20.2.
“the damages for which the Contractor shall be liable” (FIDIC 1.1.28)
On the Aldermere project
Red Book Delay Damages are GBP 4,000 a day, capped at GBP 840,000.
Where you meet it