NEC4 · ECC 11.2(2)

Completion

When the Contractor has done the work the Scope requires by the Completion Date and fixed any notified Defect that would stop the Client using the works or Others working.

The contract's words

“corrected notified Defects which would have prevented the Client from using the works” (11.2(2))

On the Aldermere project

Merrow Vale reached Completion on 26 May 2027, one day after the Completion Date of 25 May 2027.