NEC4 · ECC 11.2(3)
Completion Date
The date the Contractor must reach Completion by. It starts as the date written in the Contract Data and moves only under the contract, such as through compensation events.
“the completion date unless later changed in accordance with the contract” (11.2(3))
On the Aldermere project
The Completion Date of 30 April 2027 became 7 May 2027 when CE007 was implemented on 5 May 2026.