Waleed Tariq Academy

NEC4 · ECC 11.2(3)

Completion Date

The date the Contractor must reach Completion by. It starts as the date written in the Contract Data and moves only under the contract, such as through compensation events.

The contract's words

“the completion date unless later changed in accordance with the contract” (11.2(3))

On the Aldermere project

The Completion Date of 30 April 2027 became 7 May 2027 when CE007 was implemented on 5 May 2026.

Also written as

  • completion date

Where you meet it