NEC4 · ECC 31.1
first programme
The programme due by the Contract Data deadline when none is identified. Until a complete one is submitted, a quarter of the Price for Work Done to Date is retained.
On the Aldermere project
At the first assessment date, 9 February 2026, GBP 78,000 was retained, a quarter of the GBP 312,000 Price for Work Done to Date.
Also written as
- first programmes
Where you meet it
- Module 7: The programmePractitioner Course
- Module 3: What comes off: retention and the other secondary OptionsPayment and Defined Cost
- Module 2: Starting out and the programmeNEC4 vs FIDIC 2017