first programme

The programme due by the Contract Data deadline when none is identified. Until a complete one is submitted, a quarter of the Price for Work Done to Date is retained.

On the Aldermere project

At the first assessment date, 9 February 2026, GBP 78,000 was retained, a quarter of the GBP 312,000 Price for Work Done to Date.