NEC4 · ECC 50.5
first programme hold
Where the Contract Data names no programme, a quarter of the work done is held back from each assessment until a first programme is in. Not the contract's name.
Also written as
- first programme retention
Where you meet it
- Module 3: What comes off: retention and the other secondary OptionsPayment and Defined Cost