NEC4 · ECC Contract Data part one

defects date

The end of the period after Completion in which Defects are notified. The Contract Data sets how many weeks after Completion it falls.

On the Aldermere project

Completion was on 26 May 2027, so the defects date, 52 weeks later, is 24 May 2028.