NEC4 · ECC 11.2(7)
Defects Certificate
The Supervisor's certificate at the end of the defects stage. It lists the notified Defects still not corrected, or says none remain. The final assessment follows within four weeks.
“a list of Defects that the Supervisor has notified before the defects date” (11.2(7))
On the Aldermere project
Defect 2 was corrected on 26 May 2028, so the Defects Certificate was issued that day.
Where you meet it
- Module 8: Compensation events: what they are and how to notify themPractitioner Course
- Module 10: PaymentPractitioner Course
- Module 13: Completion, take over and DefectsPractitioner Course
- Module 14: The final assessment and closing outPractitioner Course
- Module 2: Assessment dates, applications and certificatesPayment and Defined Cost
- Module 3: What comes off: retention and the other secondary OptionsPayment and Defined Cost
- Module 12: The Contractor's share and the final accountPayment and Defined Cost
- Module 11: Risk, liability and insuranceNEC4 vs FIDIC 2017
- Module 12: Completion, defects and the final accountNEC4 vs FIDIC 2017
- Module 11: Your contract strategyContract Preparation
- Module 2: There are no clarificationsValid compensation events