NEC4 vs FIDIC 2017 · Module 1 · Lesson 4 of 4
When documents conflict
Why it matters
Aldermere’s contract is a stack of documents, so which one wins a clash?
Spot it early, then use your contract’s route.
Source: ECC 17.1. FIDIC 1.5.
The rule
The ECC ranks no document, so Dana Whitfield, the Project Manager, resolves clashes
Scope changes favour the Party that did not write it.
“The Project Manager states how the ambiguity or inconsistency should be resolved” (17.1)
- Spots itEither side
- Notifies the otherAt once
- States the answerDana
- Scope change pricedFavouring the other Party63.10
Source: ECC 17.1, 60.1(1), 63.10.
The rule
The Red Book ranks its documents, Contract Agreement first
Higher beats lower, but not two parts of one document.
Contract Agreement, Letter of Acceptance, Letter of Tender
Contract Data, Special Provisions, General Conditions
Specification, Drawings, Schedules
JV Undertaking, other documents
Source: FIDIC 1.5.
The rule
A Red Book discrepancy goes to Dana by Notice, and she clarifies
Send the Notice even when the list seems to settle it.
Think it is a Variation? Notice under 3.5 before starting (Module 6).
- Finds itEither Party1.5
- Notice to DanaPromptly1.5
- Clarifies or instructsDana1.5
- Variation? NoticeBefore starting3.5
Source: FIDIC 1.5, 3.5.
See it on the project
Aldermere’s documents line up across the versions, but only the Red Book ranks them
Know each document’s rank before a clash.
| Topic | ECC | Red Book |
|---|---|---|
| The agreement | Contract Data parts one and two. Contract Date 5 January 2026 | Contract Agreement, signed 5 January 2026, ranked first. Letter of Acceptance, ranked secondSub-Clauses 1.5, 1.6 |
| What to build | The Scope. It names the portal and has Merrow Vale Civils, the Contractor, design the wet well | The Specification, ranked seventh. It too has Merrow Vale design the wet wellSub-Clause 1.5 |
| The ground | Site Information | Site data the Employer makes availableSub-Clause 2.5 |
| The price | Activity Schedule, from Contract Data part two | Bill of Quantities, in the Schedules. Ranked ninthSub-Clause 1.5 |
| If two clash | Notify at once. Dana states how to resolve itClause 17.1 | Higher rank prevails. A Notice to Dana, who clarifies or instructsSub-Clause 1.5 |
Decide first
Red Book. Part A says GBP 4,000 a day, a Schedule GBP 3,000. Which stands?
FIDIC 1.5
ECC. Dana spots a Scope clash. Must she wait for Merrow Vale?
ECC 17.1
Source: ECC 17.1, Contract Data parts one and two. FIDIC 1.5, 1.6, 2.5.
Try it
Suppose these clashes turn up, and sort each by how it is settled
Hint: first ask which contract. Under the Red Book, then ask whether the two documents differ in rank.
…
Higher rank prevails
- Red Book. The Letter of Tender and the Specification describe the culvert lining differently.
- Red Book. The Specification and a Drawing name different joint sealants.
The list cannot settle it
- Red Book. One page of the Specification gives a pipe class that another page contradicts.
- Red Book. Two Drawings show different levels for the same run of the culvert.
ECC: Dana states how
- ECC. The Scope and the Site Information show different trench depths.
- ECC. The Activity Schedule describes the culvert differently from the Scope.
Source: ECC 17.1. FIDIC 1.5.
Quick check · When documents conflict
Two questions on what you have just covered
Hint: ask who wrote the Scope, and who may change it.
2 questions to answer
Source: ECC 17.1, 17.2, 60.1(1), 63.10.
Recap
Notify every clash early, by the route your contract gives
Clashes cost least when notified early.
On Monday at work
- ECC: notify any clash at once, as in Letter 07 (17.1).
- Red Book: give Dana a Notice promptly, even if the list settles it (1.5).
- If her answer looks like a Variation, give a Notice under 3.5 before starting.
In the Toolkit: NEC4 ECC Notice Letters (zip) Members
Independent course material. It is not published or endorsed by NEC or FIDIC. Clause references are to the NEC4 Engineering and Construction Contract (June 2017 with amendments January 2023) and the FIDIC Conditions of Contract for Construction, Second Edition 2017 as first published. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 17.1, 17.2. FIDIC 1.5, 3.5.
Go deeper (optional)
The whole module side by side, for when you need a quick reminder
A summary to come back to. Tap a tab for the part you need.
| Topic | ECC | Red Book |
|---|---|---|
| How it is built | Core clauses and the chosen Options, with Contract Data in two parts | General Conditions, changed by the Particular ConditionsSub-Clauses 1.1.9, 1.1.59 |
| Runs the contract | The Project Manager. Not a Party. Alone changes the ScopeClause 14.3 | The Engineer, appointed by the Employer. Not a PartySub-Clause 3.1 |
| How they act | As the contract states, with mutual trust and co-operationClauses 10.1, 10.2 | For the Employer, but neutrally when agreeing or determining. Cannot amend the ContractSub-Clauses 3.2, 3.7 |
| Contractor’s side | No set representative. Key persons namedClause 24.1 | The Contractor’s Representative gives every NoticeSub-Clause 4.3 |
| Topic | ECC | Red Book |
|---|---|---|
| Delegation | Any action, once the Contractor is notifiedClause 14.2 | By Notice to both Parties. Never 3.7 work or a Notice to CorrectSub-Clause 3.4 |
| Replacement | The Client names the replacement. No notice periodClause 14.4 | Notice at least 42 days ahead. Objection within 14 daysSub-Clause 3.6 |
| Topic | ECC | Red Book |
|---|---|---|
| Form | “in a form which can be read, copied and recorded” (13.1). Notifications go aloneClause 13.7 | In writing, headed as a Notice, from the named person’s own addressSub-Clause 1.3 |
| Takes effect | As it passes through the portal the Scope namesClause 13.2 | When received. A portal Notice is deemed received next daySub-Clause 1.3 |
| Replies | Within the period for reply. Extended only by agreement in timeClauses 13.3, 13.5 | No general period. Each Sub-Clause sets its ownSub-Clause 4.4.1 |
| Clashes | No ranking. Dana states how to resolve itClause 17.1 | A priority list, then a Notice to the EngineerSub-Clause 1.5 |
Source: ECC 10.1, 10.2, 11.2(13), 13.1, 13.2, 13.3, 13.5, 13.7, 14.2, 14.3, 14.4, 17.1, 24.1. FIDIC 1.1.9, 1.1.59, 1.3, 1.5, 3.1, 3.2, 3.4, 3.6, 3.7, 4.3, 4.4.1.