NEC4 vs FIDIC 2017 · Module 1 · Lesson 4 of 4

When documents conflict

8 screensAbout 7 minutes

Why it matters

Aldermere’s contract is a stack of documents, so which one wins a clash?

Spot it early, then use your contract’s route.

No rankingECC: no document outranks another
11 ranks: a priority list orders the documents
Suppose a Schedule gives GBP 3,000 a day for delay, Part A GBP 4,000. Which wins?

Source: ECC 17.1. FIDIC 1.5.

The rule

The ECC ranks no document, so Dana Whitfield, the Project Manager, resolves clashes

Scope changes favour the Party that did not write it.

“The Project Manager states how the ambiguity or inconsistency should be resolved” (17.1)

ECC

  1. Spots itEither side
  2. Notifies the otherAt once
  3. States the answerDana
  4. Scope change pricedFavouring the other Party63.10

Source: ECC 17.1, 60.1(1), 63.10.

The rule

The Red Book ranks its documents, Contract Agreement first

Higher beats lower, but not two parts of one document.

1 to 3Agreement

, ,

4 to 6Conditions

, ,

7 to 9Technical

, ,

10 and 11The rest

, other documents

Source: FIDIC 1.5.

The rule

A Red Book discrepancy goes to Dana by Notice, and she clarifies

Send the Notice even when the list seems to settle it.

Red Book

Think it is a ? under 3.5 before starting (Module 6).

  1. Finds itEither Party1.5
  2. Notice to DanaPromptly1.5
  3. Clarifies or instructsDana1.5
  4. Variation? NoticeBefore starting3.5

Source: FIDIC 1.5, 3.5.

See it on the project

Aldermere’s documents line up across the versions, but only the Red Book ranks them

Know each document’s rank before a clash.

TopicECCRed Book
The agreementContract Data parts one and two. Contract Date 5 January 2026Contract Agreement, signed 5 January 2026, ranked first. Letter of Acceptance, ranked secondSub-Clauses 1.5, 1.6
What to buildThe Scope. It names the portal and has Merrow Vale Civils, the Contractor, design the wet wellThe Specification, ranked seventh. It too has Merrow Vale design the wet wellSub-Clause 1.5
The groundSite InformationSite data makes availableSub-Clause 2.5
The priceActivity Schedule, from Contract Data part twoBill of Quantities, in the Schedules. Ranked ninthSub-Clause 1.5
If two clashNotify at once. Dana states how to resolve itClause 17.1Higher rank prevails. A Notice to Dana, who clarifies or instructsSub-Clause 1.5

Decide first

Red Book. Part A says GBP 4,000 a day, a Schedule GBP 3,000. Which stands?

GBP 4,000. Part A, the Contract Data, ranks fourth and the ninth. Owen Hale, the Contractor’s Representative, still gives Dana a Notice of the discrepancy, promptly.

FIDIC 1.5

ECC. Dana spots a Scope clash. Must she wait for Merrow Vale?

No. Either one notifies the other as soon as it becomes aware. Dana notifies Merrow Vale, then states how the clash is resolved.

ECC 17.1

Source: ECC 17.1, Contract Data parts one and two. FIDIC 1.5, 1.6, 2.5.

Try it

Suppose these clashes turn up, and sort each by how it is settled

Hint: first ask which contract. Under the Red Book, then ask whether the two documents differ in rank.

Clash 1 of 6

…

Source: ECC 17.1. FIDIC 1.5.

Quick check · When documents conflict

Two questions on what you have just covered

Hint: ask who wrote the Scope, and who may change it.

Quick checkPick an answer to see if you are right and why
1ECC. Dana resolves a clash in the Scope Aldermere Water, the Client, wrote, and her answer changes the Scope. How is the assessed?
On the reading that favours Aldermere Water
On the reading that favours Merrow Vale
On the reading Dana thinks fairest
2ECC. Merrow Vale finds that the Scope asks for something impossible. What follows once it notifies Dana?
Dana instructs a change to the Scope
Merrow Vale builds as much as it can
The Adjudicator decides what to build

2 questions to answer

Source: ECC 17.1, 17.2, 60.1(1), 63.10.

Recap

Notify every clash early, by the route your contract gives

Clashes cost least when notified early.

On Monday at work

  • ECC: notify any clash at once, as in Letter 07 (17.1).
  • Red Book: give Dana a Notice promptly, even if the list settles it (1.5).
  • If her answer looks like a Variation, give a Notice under 3.5 before starting.

In the Toolkit: NEC4 ECC Notice Letters (zip) Members

Next: the module check

Your place is kept in this browser. Create a free account to keep it on every device.

Independent course material. It is not published or endorsed by NEC or FIDIC. Clause references are to the NEC4 Engineering and Construction Contract (June 2017 with amendments January 2023) and the FIDIC Conditions of Contract for Construction, Second Edition 2017 as first published. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: ECC 17.1, 17.2. FIDIC 1.5, 3.5.

Go deeper (optional)

The whole module side by side, for when you need a quick reminder

A summary to come back to. Tap a tab for the part you need.

TopicECCRed Book
How it is builtCore clauses and the chosen Options, with Contract Data in two partsGeneral Conditions, changed by the Particular ConditionsSub-Clauses 1.1.9, 1.1.59
Runs the contract. Not a Party. Alone changes the ScopeClause 14.3, appointed by the Employer. Not a PartySub-Clause 3.1
How they actAs the contract states, with mutual trust and co-operationClauses 10.1, 10.2For the Employer, but neutrally when agreeing or determining. Cannot amend the ContractSub-Clauses 3.2, 3.7
Contractor’s sideNo set representative. Key persons namedClause 24.1The gives every NoticeSub-Clause 4.3
TopicECCRed Book
DelegationAny action, once the Contractor is notifiedClause 14.2By Notice to both Parties. Never 3.7 work or a Notice to CorrectSub-Clause 3.4
ReplacementThe Client names the replacement. No notice periodClause 14.4Notice at least 42 days ahead. Objection within 14 daysSub-Clause 3.6
TopicECCRed Book
Form“in a form which can be read, copied and recorded” (13.1). Notifications go aloneClause 13.7In writing, headed as a Notice, from the named person’s own addressSub-Clause 1.3
Takes effectAs it passes through the portal the Scope namesClause 13.2When received. A portal Notice is deemed received next daySub-Clause 1.3
RepliesWithin the period for reply. Extended only by agreement in timeClauses 13.3, 13.5No general period. Each Sub-Clause sets its ownSub-Clause 4.4.1
ClashesNo ranking. Dana states how to resolve itClause 17.1A priority list, then a Notice to the EngineerSub-Clause 1.5

Source: ECC 10.1, 10.2, 11.2(13), 13.1, 13.2, 13.3, 13.5, 13.7, 14.2, 14.3, 14.4, 17.1, 24.1. FIDIC 1.1.9, 1.1.59, 1.3, 1.5, 3.1, 3.2, 3.4, 3.6, 3.7, 4.3, 4.4.1.