NEC4 ECC Practitioner Course · Module 1 · Lesson 2 of 4
Who is who
Why it matters
Dana is not a Party, so is she bound by the two-week period for reply?
Dana Whitfield is the Project Manager, Tom Barrow the Supervisor.
Source: ECC 11.2(13). Aldermere Contract Data part one.
The rule
Dana and Tom act for the Client but are not Parties
The Parties are “the Client and the Contractor” (11.2(13)).
The Client.
The Contractor, which Provides the Works.
The Project Manager. Instructs, replies, certifies payment.
The Supervisor. Watches tests, notifies Defects.
Source: ECC 11.2(13), 13.4, 14.3, 20.1, 41.3, 43.2, 51.1.
The rule
Clause 10 binds the Project Manager and the Supervisor as well as the Parties
Not being a Party frees nobody from the rules.
So time limits such as the period for reply bind Dana.
All four “act in a spirit of mutual trust and co-operation” (10.2).
Source: ECC 10.1, 10.2.
The rule
A firm's work decides if it is a Subcontractor
Judge a firm by what it does.
Yes, if it
- builds or installs part of the works
- designs part of the works
- gives a needed service in the Working Areas
No, if it only
- designs its own Plant and Materials
- hires out Equipment
- supplies people paid for time worked
Source: ECC 11.2(19).
See it on the project
Dana accepts Cobalt, a Subcontractor, first
Leila Moss is Merrow Vale's commercial manager.
- 14 JanLeila sends Dana Cobalt's name.
- 23 JanDana accepts Cobalt (26.2).
- 26 JanCobalt is appointed on an unamended ECS (26.3).
Are the utility firms under Station Road Subcontractors?
Does accepting Cobalt move responsibility off Merrow Vale?
Source: ECC 11.2(12), 11.2(19), 26.1, 26.2, 26.3. Aldermere storyline.
Try it
Sort the six firms Leila meets in January
Test each firm against the three limbs and the two exclusions you just saw.
…
Subcontractor
- Cobalt Pumps supplies and installs the pumps and controls.
- A firm cleans and services the welfare cabins in the Working Areas.
Not a Subcontractor
- A plant firm hires an excavator to Merrow Vale.
- A valve maker designs and delivers its own valves. It does no work on the Site.
- An agency supplies labourers who are paid by the hour.
- A utility company moves its own apparatus under Station Road.
Source: ECC 11.2(12), 11.2(19), 26.2.
Quick check · Who is who
Two questions on what you have just covered
Answer, then read why.
2 questions to answer
Source: ECC 10.1, 26.1.
Recap
Know who may act, and test each firm by what it does
The Checklists' Setup tab sets the form of contract and time limits.
On Monday at work
- List the Parties, the Project Manager and the Supervisor for your job.
- Test each new firm against clause 11.2(19).
- Send each Subcontractor's name to Dana before you appoint it.
In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members
Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 11.2(13), 11.2(19), 26.2.
Go deeper (optional)
Dana and Tom each hold their own actions
Optional. Whose desk each task sits on.
Dana, the Project Manager
- Instructs (14.3)
- Replies to submissions (13.4)
- Assesses the amount due (50.1)
- Certifies payment (51.1)
Tom, the Supervisor
- May watch any test (41.3)
- Instructs searches for Defects (43.1)
- Notifies Defects (43.2)
- Issues the Defects Certificate (44.3)
Source: ECC 13.4, 14.3, 41.3, 43.1, 43.2, 44.3, 50.1, 51.1.
Go deeper (optional)
The Defects Certificate can come on the defects date or later
Optional. A date that matters years later, at the end of the job.
No notified Defect is left at the defects date. When does Tom issue it?
ECC 44.3
Some notified Defects are still open then. When does it come?
ECC 44.3
Source: ECC 44.3.
Go deeper (optional)
Subcontracting keeps the risk and passes the duty down
Optional. What subcontracting changes, and what it does not.
Does subcontracting move any risk?
ECC 26.1
May Dana refuse a subcontract's documents?
ECC 26.3
Why did Cobalt's ECS not go to Dana?
ECC 26.3. ECS 10.2
Source: ECC 26.1, 26.3. ECS 10.2.