NEC4 Contract Preparation · Lesson 2 of 3

Italics and capitals

6 screensAbout 5 minutes

Why it matters

By June 2026 part one says 30 April 2027, but the date has moved

Compensation events move the date. Lesson 3 shows how.

30 Apr 2027the completion date entry in part one
7 May 2027the once compensation event CE007 is implemented
Which does the programme follow? The type tells you.

Source: ECC 11.2(3), 66.2.

The rule

Italics point to the Contract Data, capitals to a definition

The type tells you where to look.

Italics

See the Contract Data. “terms identified in the Contract Data are in italics” (11.1).

completion date, fee percentage, period for reply

Capitals

Defined, mostly in clause 11.2.

Completion Date, Fee, Project Manager

Plain lower case terms are explained where used.

Source: ECC 11.1.

The rule

The entry stays put, while the defined term moves with change

Plan to the defined term as it stands today.

The Completion Date is “the completion date unless later changed in accordance with the contract” (11.2(3)).

Part one entry (italics)

A works the same way (11.2(11)).

Source: ECC 11.2(3), 11.2(11).

See it on the project

The Completion Date ends at 25 May 2027 after two compensation events and an adjudication

Part one never moves. Decide, then tap to check.

Days added to 30 April 2027

Part one entryNever changes
30 Apr 2027
CE007 implemented5 May 2026
77 May 2027
CE014 assessed20 July 2026
1219 May 2027
Adjudicator's decision30 Oct 2026
625 May 2027
0+7+14+21+28

The decides disputes under W1.

The Contractor's revised programme goes in on 7 September 2026. Which completion date must it show?

19 May 2027, the Completion Date as it stood that day: 30 April plus 7 days for CE007 and 12 for CE014. The Adjudicator's 6 days come later, on 30 October (11.2(3), 31.2).

ECC 11.2(3)

Source: ECC 11.2(3), 66.2.

Try it

Sort each term by where its meaning is

Six terms. Each answer says where the meaning is.

Hint: look at the type. Italic, capitals or plain lower case.

Term 1 of 6

…

Source: ECC 11.1, 11.2.

Recap

Read the type of a term before you read its meaning

Habits that keep you on the right date.

On Monday at work

  • Check an italic term against the Contract Data (11.1).
  • Find a capitalised term in clause 11.2 or the clauses.
  • Plan to the Completion Date as it stands today (11.2(3)).

In the Toolkit: NEC4 Contract Checklists (ECC and ECS) (Excel) Members

Next lesson: Sections and compensation events

Your place is kept in this browser. Create a free account to keep it on every device.

Independent course material. It is not published or endorsed by NEC. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023, unless another NEC4 contract is named. The project and the people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.

Source: ECC 11.1, 11.2(3), 66.2.

Go deeper (optional)

Four terms people often misread

Open any you are unsure of.

Is Dana Whitfield a ?

No. Only and the Contractor are Parties. Dana acts for the Client.

ECC 11.2(13)

Is a firm that only supplies the pumps a ?

No. A Subcontractor builds, installs or designs part of the works.

ECC 11.2(19)

What passes to the Client at ?

Possession of the works and most risk of loss.

ECC 35, 80.1

What do Employer and Works Information mean today?

Client and Scope. The Adjudicator's Contract became the Dispute Resolution Service Contract.

NEC4 ECC

Source: ECC 11.2(13), 11.2(19), 80.1.