NEC Case Law, Clause by Clause · Module 1 · Lesson 3 of 4
Changing the contract
Why it matters
Does a director's remark that a day late will not matter stop the deduction?
A remark at a meeting, and nothing written down.
Source: ECC 12.3, X7.1.
The rule
Any other change needs both Parties to sign it
Only the Parties sign. Dana, the Project Manager, cannot.
- 1
Do the conditions provide for the change?
If yes:It takes effectSuch as a Scope changeIf no, go on to question 2. - 2
Is it “agreed, confirmed in writing and signed by the Parties” (12.3)?
If yes:It takes effectIf no, go on to the outcome. - No effect
Source: ECC 12.3, 14.3.
The rule
Clauses that demand signed changes work
12.3 is a no oral modification clause. The Privy Council followed Rock in 2026 (Module 8).
The facts
Rock said a phone call agreed new payment dates.
Held
Such clauses stop informal deals and control who agrees changes.
Source: Rock Advertising v MWB (2018). ECC 12.3.
The rule
Shared practice can bind for the past
NEC3 Term Service Contract.
The dispute
- Jul 2009 to Jan 2010About 13,600 orders on agreed codes.
- Jan 2010Shoreline seeks about GBP 300,000.
Three judgments
- 17 Jan 2013TCC: no strike out.
- 5 Jun 2013Court of Appeal: agreed.
- 20 May 2015Trial: estoppel by convention protects earlier months.
Source: Mears v Shoreline (2013 and 2015). NEC3 TSC 12.3, 12.4.
See it on the project
The remark changes nothing, so the GBP 4,000 deduction stands
A remark alone is no estoppel either.
- 112 MayWhat ifAldermere Water What if: a director says a day late will not matter. Nothing written, nothing signed (12.3).
- 226 MayCompletionMerrow Vale Completion, one day after the Completion Date. Aldermere Water deducts GBP 4,000 (X7).
…
Source: ECC 12.3, X7.1. Rock Advertising v MWB (2018).
Try it
Predict what each court held, then tap to check
Say yes or no before you tap.
Rock: did the phone call vary a licence that needed signed changes?
Rock: is estoppel gone?
Mears: could Shoreline claw back the months before its notice?
Mears: after the notice, did the codes still bind?
Source: Rock Advertising v MWB (2018). Mears v Shoreline (2015).
Try it
Sort each step: does it take effect or not?
Ask two questions each time. Do the conditions allow it, and did both Parties sign?
…
Takes effect
- Dana instructs a flatter slope on the embankment, a change to the Scope.
- Dana and Leila Moss, Merrow Vale's commercial manager, agree rates to price a compensation event.
- Both Parties sign a change to the retention free amount, each through a director.
No effect
- Progress meeting minutes say all retention will be released at Completion. Nobody signs.
- Raj Patel, Merrow Vale's planner, and the Supervisor Tom Barrow agree to skip a required test.
- A director of Aldermere Water tells Leila by phone that delay damages are waived. Nothing else happens.
Source: ECC 12.3, 14.3, 60.1(1), 63.2, X16.
Recap
Get every change signed, or end an informal practice by notice
Remarks and minutes change nothing. A signed change does.
On Monday at work
- Check first whether the conditions provide for the change.
- Put any other change in one document both Parties sign (12.3).
- When practice drifts from the contract, sign it or end it by notice.
In the Toolkit: NEC4 ECC Notice Letters (zip) Members
Independent course material. It is not published or endorsed by NEC, and it is not legal advice. Clause references are to the NEC4 Engineering and Construction Contract, June 2017 with amendments January 2023. Cases decided under an earlier edition are matched to the NEC4 clause that does the same job. The worked examples and their people are invented. Short quotes from NEC4 (© NEC 2017) and the FIDIC Red Book (© FIDIC 2017) are used for review and comment. Read the full clauses in your own copy of the contract.
Source: ECC 12.3, 63.2.
Go deeper (optional)
Write a change both Parties can sign
Name each Party exactly.
Aldermere Water and Merrow Vale Civils Ltd agree:
[clause or entry] reads [new words] from [date]
For Aldermere Water: [name, position]
For Merrow Vale Civils Ltd: [name, position]
No Toolkit letter: both Parties sign this.
Source: ECC 12.3.
Go deeper (optional)
Two points on clause 12.3 that no court has settled
Open questions for later.
Does estoppel still get round 12.3 after Rock?
Mears (2015). Rock (2018)
What counts as signed under 12.3?
ECC 12.3
Source: ECC 12.3. Mears (2015). Rock (2018).