NEC4 · ECC 11.2(20)
Working Areas
The Site plus the working areas named in the Contract Data that are needed for the work and used only for this contract. Many Defined Cost rules turn on it.
“the Site and those parts of the working areas” (11.2(20))
Also written as
- working areas
Where you meet it