NEC4 · ECC 35.1
take over
When the Client takes the works into its care and use. This is normally within two weeks of Completion. Using a part early usually counts as taking it over.
On the Aldermere project
Aldermere Water took over the works on 26 May 2027, the day of Completion.
Also written as
- taken over
- takes over
- took over
Where you meet it
- Module 13: Completion, take over and DefectsPractitioner Course
- Module 5: Design, Defects and insuranceCase Law
- Module 11: Your contract strategyContract Preparation