NEC4 · ECC 32.2
revised programme
An updated programme showing actual progress and how the Contractor will deal with delays. It is due at the Contract Data interval and whenever the Project Manager instructs.
On the Aldermere project
Aldermere's revised programmes are due at intervals no longer than four weeks.
Also written as
- revised programmes
Where you meet it
- Module 7: The programmePractitioner Course