quotation

The Contractor's priced offer for a compensation event. It proposes the change to the Prices and how far the Completion Date and each Key Date should move.

On the Aldermere project

Merrow Vale's first CE007 quotation, on 30 March 2026, was GBP 86,400 and 9 days of delay to planned Completion.