NEC4 · ECC Option C 11.2(31)
Price for Work Done to Date
The basis of each payment. Under Option C it is the Fee plus the Defined Cost the Project Manager expects to be paid out before the next assessment.
“the total Defined Cost which the Project Manager forecasts will have been paid” (11.2(31))
On the Aldermere project
At the 4 May 2026 assessment, Defined Cost of GBP 1,900,000 plus the Fee of GBP 209,000 gave GBP 2,109,000.