FIDIC 2017 · FIDIC 1.1.62
Performance Certificate
The Engineer's certificate that the Contractor has completed its obligations, due within 28 days after the Defects Notification Period ends. It alone counts as acceptance of the Works.
“the certificate issued by the Engineer (or deemed to be issued)” (FIDIC 1.1.62)
On the Aldermere project
Dana issued the Performance Certificate on 12 June 2028, stating 26 May 2028 as the date obligations were fulfilled.
Where you meet it
- Module 12: Completion, defects and the final accountNEC4 vs FIDIC 2017