NEC4 · ECC Option X7
Option X7
Delay damages. The Contractor pays a stated daily sum if Completion, or earlier take over, comes after the Completion Date.
On the Aldermere project
Aldermere uses X7 at GBP 4,000 a day.
Also written as
- X7
Where you meet it
- Module 5: X Options and Z clauses: what to add and what to leave outContract Preparation