Waleed Tariq Academy

NEC4 · ECC Option X22

Option X22

Early Contractor involvement, for Options C and E. The Contractor helps develop and price the design in Stage One, then builds it in Stage Two.

Also written as

  • X22
  • early Contractor involvement

Where you meet it