NEC4 · ECC W1.3(1)
notice of adjudication
The notice that starts an adjudication. Under W1 it comes within two weeks after the Senior Representatives list the issues, and the referral within a week after that.
On the Aldermere project
For CE014, the notice of adjudication went on 1 September 2026 and the referral on 7 September.