NEC4 · ECC 11.2(13)
Parties
The two sides bound by the ECC: the Client and the Contractor. Roles such as the Project Manager are not Parties.
“the Client and the Contractor” (11.2(13))
On the Aldermere project
Aldermere Water and Merrow Vale Civils Ltd are the Parties. Dana Whitfield and Tom Barrow are not.
Also written as
- Party
- the Parties
Where you meet it
- Module 1: How the ECC fits togetherPractitioner Course · Free