FIDIC 2017 · FIDIC 1.1.45

Interim Payment Certificate

The Engineer's Payment Certificate for an interim payment, issued within 28 days of the Statement arriving. It must show and explain any amount withheld.

The contract's words

“a Payment Certificate issued by the Engineer for an interim payment” (FIDIC 1.1.45)

On the Aldermere project

Dana issued the IPC on 29 May 2026 for GBP 539,000, withholding GBP 12,000 for two culvert joints.

Also written as

  • IPC
  • IPCs
  • Payment Certificate
  • Payment Certificates