NEC4 · ECC 27.3

instruction

A direction from the Project Manager or the Supervisor that the Contractor must obey if it follows the contract. A Scope change by instruction is usually a compensation event.

On the Aldermere project

On 1 June 2026 Dana instructed a flatter slope on the embankment.

Also written as

  • instructions