NEC4 · ECC Option C 54.1
increment
The part of the gap between planned and actual cost that falls inside one share range. Each increment is multiplied by that range's percentage.
Also written as
- increments
Where you meet it
- Module 12: The Contractor's share and the final accountPayment and Defined Cost