NEC4 · ECC 63.1
forecast Defined Cost
The Defined Cost of work not yet done at the dividing date, estimated when the compensation event is assessed. The assessment is not revised later (66.3).
Where you meet it
- Module 8: The Short Schedule and pricing compensation eventsPayment and Defined Cost