FIDIC 2017 · FIDIC 1.1.5
Bill of Quantities
Under the Red Book, the priced list of work items in the Schedules. Work is measured and paid at its rates, which change if quantities change enough.
“the document entitled bill of quantities (if any) included in the Schedules” (FIDIC 1.1.5)
On the Aldermere project
The Bill rate for imported fill is GBP 14.00, so 9,000 m3 of extra fill is GBP 126,000.
Also written as
- Bill
- Bill rate
- Bill rates