Fee

Defined Cost multiplied by the fee percentage. It covers every cost that is not Defined Cost, such as head office overheads, plus profit.

The contract's words

“the amount calculated by applying the fee percentage to the amount of Defined Cost” (11.2(10))

On the Aldermere project

In CE007, Defined Cost of GBP 73,153.15 attracts a Fee at 11% of GBP 8,046.85.