FIDIC 2017 · FIDIC 1.1.38
Extension of Time
Extra time added to the Time for Completion, earned under Sub-Clause 8.5 and claimed through Sub-Clause 20.2. The ECC moves the Completion Date through compensation events instead.
“an extension of the Time for Completion under Sub-Clause 8.5” (FIDIC 1.1.38)
On the Aldermere project
The DAAB's Variation 1 decision gave an EOT of 18 days, so the Time for Completion ran to 25 May 2027.
Also written as
- EOT
- EOTs
Where you meet it
- Module 8: Extending time and delay damagesNEC4 vs FIDIC 2017