FIDIC 2017 · FIDIC 1.1.38

Extension of Time

Extra time added to the Time for Completion, earned under Sub-Clause 8.5 and claimed through Sub-Clause 20.2. The ECC moves the Completion Date through compensation events instead.

The contract's words

“an extension of the Time for Completion under Sub-Clause 8.5” (FIDIC 1.1.38)

On the Aldermere project

The DAAB's Variation 1 decision gave an EOT of 18 days, so the Time for Completion ran to 25 May 2027.

Also written as

  • EOT
  • EOTs