NEC4 · ECC 11.2(9)
Equipment
Things the Contractor provides and uses to Provide the Works but is not required to build in, such as an excavator or a site cabin.
“the Scope does not require the Contractor to include in the works” (11.2(9))
On the Aldermere project
The breaker hired to break out the CE007 concrete is Equipment.
Where you meet it