NEC4 · ECC 15.1
early warning
A prompt notice of a matter that could add cost or delay, or harm the works in use. The Contractor and Project Manager both give them.
On the Aldermere project
Raj Patel gave an early warning on 3 March 2026, the day the buried concrete was found.
Also written as
- early warnings
Where you meet it
- Module 5: Early warningsPractitioner Course
- Module 10: Disallowed Cost, ground by groundPayment and Defined Cost
- Module 7: Early warning, prevention events and accelerationCase Law
- Module 4: Early warning and advance warningNEC4 vs FIDIC 2017