NEC4 · ECC 11.2(8)

Early Warning Register

The Project Manager's list of risk matters, from the Contract Data or early warnings, and how each will be avoided or reduced. It is revised after each early warning meeting.

The contract's words

“notified by the Project Manager or the Contractor as early warning matters” (11.2(8))

On the Aldermere project

Dana issued the first Early Warning Register on 16 January 2026 and a revised one on 10 March.