NEC4 · ECC 63.1

dividing date

The date that splits a compensation event's cost into actual Defined Cost before it and forecast Defined Cost after it. It is the date of the triggering instruction or notification.

On the Aldermere project

CE007's dividing date is 6 March 2026: actual Defined Cost GBP 6,153.15 and forecast GBP 67,000.00.

Also written as

  • dividing dates