NEC4 · ECC Option C 11.2(26)

Disallowed Cost

Cost the Project Manager removes from Defined Cost, such as cost not backed by records or caused by a missed early warning. It is left out of the amount due.

The contract's words

“is not justified by the Contractor’s accounts and records” (11.2(26))

On the Aldermere project

Dana's check of the four weeks to 29 June 2026 found Disallowed Cost of GBP 10,000.